Friday, April 11, 2008

End of Week 4

Drywall is up and the mudding and taping has begun. Oddly enough the rooms feel a bit smaller to me with the drywall up, especially the office space. With that wall extention coming out another 3 1/2 inches, it really feels like it's going to be tight putting a chair in there and still being able to get out the side door.

I checked with Dave today about when he would like us to schedule the granite install and he suggested the first full week in May. Cabinets should go in next week, but he wanted an extra week to make sure we were ready for granite. We plan to go down tomorrow to talk to our granite guy to get the install lined up.





1 comment:

Kathryn said...

Met with our granite guy this morning and scheduled the granite install for May 5th. Just 3 more weeks! Better get our flooring picked out and scheduled soon.